Work is planned for Saturdays in late July/early August in order to maintain project timeline
July 17, 2024
  • The first phase of the Realize Flood Park project has been in progress since mid-April. Contractors have excavated concrete, tennis courts, some grass areas and picnic sites in preparation for construction of a multi-use sports field, new picnic areas, and sports courts —basketball, tennis/pickleball, and sand volleyball.

    With the goal of maintaining the project timeline, contractors will work the following Saturdays: July 20 and 27 and August 3 and 10.  Activity will not begin before 9 a.m. and will conclude at least by 5 p.m.  The bike pump track will be open on these days.  We’re reminding cyclists to be aware of trucks moving in and out of the park and follow directions by safety flaggers.

    Work during this period will include irrigation installation and the removal and preservation of trees scheduled to be transplanted elsewhere in the park. To the extent possible this work will not occur near residences.