All Projects

Project No. RW302; Project File No. E5080

Location

West Menlo Park, Ladera, Alpine Road (Ladera), Middlefield Road (between 5th and 8th)

About the Project

The 2023-2024 ADA Ramp Program will evaluate and replace ADA ramps prior to construction of the 2023 and 2024 Pavement Preservation Projects.

Public Works Contact

Alex Zhang
Senior Engineer 
azhang@smcgov.org
650-363-4100

Contractor

TBD

UPDATES
  • November 2022 - Start of project development and design. Develop GIS Application to collect data.
  • January 2023 - Conduct desktop/preliminary review of ramps based off of Road Surfacing Projects Lists.
  • July 2023 - Finalizing list of ramps to be updated.
  • December 2023 - Finalized Ramp List.
  • March 2024 - Research and refine ramp replacement criteria.
  • April 2024 - 60% Plans, Specifications, and Estimates in Development.
  • May 2024 - 60% PSE Review. 90% PSE Development.
  • June 2024 - 90% PSE Development.
  • July 2024 - Continue 90% PSE Development.
  • August 2024 - Design to be finalized and advertised for bids in August 2024.
  • September 2024 - Bid Opening took place on August 29, 2024. John Boylan Engineering, Inc. was the lowest responsible bidder. The project will be awarded on September 10, 2024.
  • October 2024 - Construction is anticipated to begin in October.
  • November 2024 - Construction On-going. Reconstruction of 11 of 39 ramps have been completed.
CALC @ Vasilakos Ct 2 ADA Ramp Concrete finishing at Wendy Wy & Valpariso a November 2024 November 2024 ADA Ramp Concrete finishing at Wendy Wy & Valpariso ADA Ramp Concrete finishing at Wendy Wy & Valpariso b November 2024 November 2024 Concrete finishing at Wendy Wy & Valpariso ADA Ramp Concrete pour at Wendy Wy & Valpariso November 2024 November 2024 Concrete pour at Wendy Wy & Valpariso ADA Ramp Demo and formwork at Lucky Ave & Avy Ave November 2024 November 2024 Demo and formwork at Lucky Ave & Avy Ave