All Projects

Project No. 08SR1; Project File No. E5093000

Location

Near 4901 Stage Road, Pescadero, CA

About the Project

The slip-out repair project will repair the failing embankments and damaged pavements. The work to be done consists, in general, of installing a retaining wall, drainage improvements, and installing a rock slope protection revetment with plantings, and erosion control/slope protection.

Public Works Contact

Joshua Rawley
Senior Civil Engineer
jrawley@smcgov.org
650-363-4100

Contractor

Al Matin
Project Manager
SBAY Construction, Inc. 
408-490-4390

UPDATES
  • January 2023 – Roadway failed due to heavy storms. Preliminary site investigations performed.
  • February 2023 - Desktop analysis, development of supporting documents for FEMA, and procurement of geotechnical and drilling firms.  
  • March 2023 - Coordination with Cal OES/FEMA and monitoring of site. Drilling schedule for March 29th and 30th. 
  • May 2023 - Field Meeting with FEMA for site assessment and repair scope development.
  • June 2023 - Received and reviewing Geotechnical Investigation Report.
  • July 2023 - Finalizing construction documents for public bid.

  • September 2023 – Entered into contract via our JOC ordering system with SBAY Construction, Inc for the Repair and Reconstruction Work. Work to commence on 9/25/23 and scheduled to 11/17/23 on Monday – Saturday 7:30 AM – 5 PM. Road closed to through traffic. Bicyclist to use alternative route.

  • December 1, 2023 – SBAY Construction Inc., has finished wall construction and paving work. Guardrail to be installed within the week of 12/4/23.

  • January 2024 - Construction has been completed and the road is now open to the public. Minor punch list items are being addressed.

  • May 2024 - Project Completion.

Stage Road #1 - Slip Out Stage Road #1 (Dec 23) December 2023 Stage Road Site #1 January 2024 January 2024