All Projects

Project No. RW409; Project File No. E5091

Location

8th Avenue from Middlefield Road to Edison Way

16th Avenue from End to approximately 789 16th Avenue

About the Project

The Project involves the roadway reconstruction of 8th Avenue from Middlefield Road to Edison Way and 16th Avenue from End to approximately 789 16th Avenue in the unincorporated North Fair Oaks Area.

Project scope also requires sanitary sewer pipe replacement, sewer manholes, and drainage infrastructure on both 8th  and 16th Avenue.

Public Works Contact

Wency Ng
Senior Civil Engineer 
wng@smcgov.org
650-363-4100

Contractor

Ghilotti Construction Company, Inc.

Construction Schedule

   â€¢    Aug 2024 – Nov 2024
   â€¢    Nov 2024 – April 2025 (Weather Moratorium)
   â€¢    April 2025 – July 2025

Note that all scheduling dates are approximate only and subject to change.  All pedestrian, bicycle, and vehicular traffic access will be limited during construction and experience delays.  Abide to traffic control signage on site during construction and detour on local streets accordingly. 

Updates
  • December 2023
    • Prepared and mailed survey letters to property owners.
  • January 2024
    • Virtual public meeting: January 10, 2024 (Wednesday) from 6:30-7:30PM via Zoom (Video).

    • Survey Due to County 01/26/2024, both 8th and 16th Avenue.​​​​​

  • February 2024
    • 60% Plans and Specification.
    • Survey results calculations.
  • March 2024
    • 90% Plans and Specifications.
    • Prepared survey results letters.
  • April 2024 
    • Sent survey results letters to property owners.
    • Advertised for bids on April 25, 2024. 
    • Bids due by Thursday, May 9, 2024.
  • ​​​​​May to June 2024
    • This project will be re-bid.
    • Advertised for re-bids on May 23, 2024.
    • Bids due by Thursday, June 13, 2024.
  • July 2024
    • Project was awarded to Ghilotti Construction Company, Inc. by County of San Mateo Board of Supervisors on June 25, 2024.
  • August 2024 – Ramping up construction and contractor mobilization. Majority of work performed will be done on 16th Ave. Work underway will include but not be limited to survey layout, potholing, USA coordination, delivering equipment/tools to site, delivering public notification letters, posting project info/traffic control signage, SWPPP BMPs, and the installation of sewer piping. Drive slowly during construction, always abide to Traffic control signage, and expect delays. 
  • September 2024 - Majority of construction work performed will be done on 16th Ave. Work underway will include but not be limited to survey layout, potholing, USA coordination, delivering equipment/tools to site, delivering public notification letters, posting project info/traffic control signage, SWPPP BMPs, and the installation of sewer piping. Drive slowly during construction, always abide to Traffic control signage, and expect delays.
  • October 2024 - Contractor is working to construct concrete valley gutters on 16th Avenue.
  • November 2024 – Majority of Construction scope on 16th Ave is completed.  Work performed on 16th Ave this month included the placement of new Asphalt road and striping.  Sewer work designated for 8th Ave should be completed by the end of this month.  Continuation of work on 8th Ave will be weather dependent.  Drive slowly during construction, always abide to Traffic control signage, and expect delays.

Subscribe for Email Updates! 

Reconstruction of 8th Ave and 16th Ave (North Fair Oaks Area) Vicinity Map Vicinity Map Reconstruction of 8th Ave Location Map 8th Ave Location Map LOCATION_MAP 1-5091_(16TH) 5-22-24 16th Ave Location Map August 2024 Reconstruction of 8th, 16th Mobilization August 2024 Mobilization August 2024 Reconstruction of 8th, 16th New SS Manhole August 2024 New SS Manhole August 2024 Reconstruction of 8th, 16th New SS Piping August 2024 New SS Piping August 2024 Reconstruction of 8th, 16th Old SS Manhole August 2024 Old SS Manhole 8th, 16th Drainage Gallery (Sep 2024) September 2024 Drainage Gallery 8th, 16th Sewer Pipe Install (Sep 2024) September 2024 Sewer Pipe Install 8th, 16th Site Planning (Sep 2024) September 2024 Site Planning 8th, 16th Valley Gutter Excavation (Sep 2024) September 2024 Valley Gutter Excavation 8th, 16th Drainage Box Install (Oct 2024) October 2024 Drainage Box Install 8th, 16th Valley Gutter Concrete (Oct 2024) October 2024 Valley Gutter Concrete Placement 8th, 16th Valley Gutter Form (Oct 2024) October 2024 Valley Gutter Form Placement Recon 8th 16th Asphalt Paving-1 November 2024 November 2024 Asphalt Paving-1 Recon 8th 16th Asphalt Paving-2 November 2024 November 2024 Asphalt Paving-2 Recon 8th 16th Roller Compaction November 2024 November 2024 Roller Compaction Recon 8th 16th Sewer Pipe Install November 2024 November 2024 Sewer Pipe Install