Project No. RW937; Project File No. 1-5049
Location
- Bunker Hill Drive from Yorktown Road and Brandywine Road at Highlands Elementary School
- Avenue Alhambra from Coronado Street to The Alameda at Wilkinson Elementary School
Reference location maps 1 and 2
About the Project
Installation of midblock crosswalks with rectangular rapid flashing beacons (RRFB), installing concrete curb extensions, curb ramps, traffic striping and markings.
Public Works Contact
650-363-4100
Contractor
Bay Area Lightworks, Inc.
Updates
February 2023 - 90% Plans and Specifications Completed.
March 2023 - 100% Plans and Specifications Completed.
April 2023 - Advertised for bids, opened bids, and awarded project to Bay Area Lightworks, Inc. Construction is anticipated to begin after school session is over in summer 2023.
May 2023 - Pre-construction meeting held on May 1, 2023. Construction is anticipated to begin in June 2023.
June 2023 - Construction in progress. Contractor began sidewalk and curb ramp improvements.
August 2023 - Contractor installed rectangular rapid flashing beacon assembly.
September 2023 - Contractor worked on punch list items.