All Projects

Project No. P29L3; Project File No. E5067

Location

1701 Coyote Point Drive, San Mateo, CA 94401

About the Project

Department assessed the condition of the existing water distribution system at Coyote Point Park and is currently working on a design for improvements to the system.

Public Works Contact

Alex Zhang
Senior Engineer 
azhang@smcgov.org
650-363-4100

Contractor

TBD

Documents

N/A

UPDATES
  • May 2022 - Begin water system assessment work at Coyote Point

  • July 2022 - Drafting condition assessment report

  • September 2022 - Review Water System Assessment Report

  • November 2022 - Final comments to Water System Assessment Report

  • December 2022 - Sent RFP for design services and received proposal

  • January 2023 - Finalized Assessment Report and currently reviewing the design services proposal

  • February 2023 - Design Proposal approved

  • March 2023 - Received 60% Design package for review

  • April 2023 - Additional research done to fill gaps in design

  • May 2023 - 60% Design Complete

  • June 2023 - 90% Design Complete

  • July 2023 - Project working towards 100% Design

  • September 2023 to Present - Project on hold.

Location Map (P29L3) Location Map