Project Dates
Bridge Construction: February 2016 - October 2018 (Completed)
PG&E Construction: February 2018 - August 2018 (Completed)
Site Security & Complete the Gap Trail Project: October 2018 - December 2018 (Current work)
Reopening of Roadway: January 11, 2019
Location
Crystal Springs Rd & Skyline Blvd
About the Project
The work to be done consists, in general, of constructing a new replacement 626 foot long by 51.5 foot wide cast-in-place, post-tensioned concrete box girder bridge on top of the Lower Crystal Springs Dam. It will be installed approximately seven feet higher than the previous bridge due to the work completed by the San Francisco Public Utilities Commission (SFPUC) to raise the parapet wall on the dam. The previous bridge has been demolished and removed from site.
The work to be done includes installing conduit support brackets for a PG&E conduit for the 230 kV electrical transmission line, grading, drainage facilities, paving, and vista point area parking lot improvements. The Project will also include coordination with PG&E’s construction crew for the installation of the 230kV electrical transmission line under the bridge and at the bridge approaches.
Contractor
Kiewit Infrastructure West Company
707-439-7300
Public Works Contact
Updates
JANUARY 4, 2019
Crystal Springs Dam Bridge Opens January 11
Pedestrians and bicyclists are invited to experience the newly reopened Crystal Springs Dam Bridge on Friday, January 11 at 2 p.m. Learn more
OCTOBER 30, 2018
Traffic delays are anticipated at Crystal Springs Road and Skyline Boulevard. Traffic advisories to be updated periodically. For more information: Road Closure Notification