Project No. RW927; Project File No. E5030
Location
Bear Gulch Road (San Gregorio Area)
About the Project
The project will replace a deteriorated 60-inch corrugated metal pipe with a 60-inch polyethelyne pipe by open trench. The improvements will also include the installation of a concrete head wall to support the new pipe and road shoulder.
Public Works Contact
Anthony Lum
Senior Engineer
alum@smcgov.org
650-363-4100
Contractor
TBD
UPDATES
- March 2022 - 90% Design completed
- May 2022 - 100% Design completed
- June 2022 - Plans and Specifications adopted by the Board on June 14th; Project currently out to bid with bid opening date on July 7th
- July 2022 - Project awarded to Rehak General Engineering on July 26th
- August 2022 - Contractor has started work and completed installing the culvert pipe
- September 2022 - Construction Status: 95% Complete
- October 2022 - Construction Status: 100% Complete
- November 2022 - Punchlist items were addressed and project is complete.
Inside of 60 Inch corrugated metal pipe to be replaced
Inside of 60 Inch corrugated metal pipe to be replaced
Culvert Outlet
RGE installing new 60 inch steel reinforced polyethene pipe
RGE laying out the concrete headwall