Project No. P30V1; Project File No. TBD
Location
1100 Kings Mountain Rd, Woodside, CA 94062
About the Project
Department shall assess the condition of the existing water distribution system at Huddart Park and consider upgrades or improvement options.
Public Works Contact
Alex Zhang
Senior Engineer (WOC)
azhang@smcgov.org
(650) 363-4100
Contractor
TBD
Documents
N/A
UPDATES
-
May 2022 - Begin water system assessment work at Huddart Park
-
July 2022 - Drafting condition assessment report
-
November 2022 - Finalizing the water system assessment report
-
January 2023 - RFP for design services and review proposal
-
June/July 2023 - Project on hold