Project No. TBD; Project File No. TBD
Location
South of Huddart Park Road
About the Project
This project is an emergency repair project that will include, in general, rehabilitating the damaged section of the road using stitch piers, base rock, asphalt pavement, and re-installing the asphalt dike and pavement markings.
Public Works Contact
650-363-4100
Contractor
TBD
UPDATES
- July 2023 - Working with Contractor to design/construct a slope stabilization repair.
- August 2023 - Starting Construction in September.
- September 2023 - Contractor stared mobilizing on 10/2 and is expected to complete the work by end of October 2023
- October 2023 - Piers have been installed. Road improvements started and expected to be completed by mid-November 2023.
- November 2023 - Paving completed. After traffic elements are installed the road will be open in December 2023.
- May 2024 - Project Completion.