Project No. RW309; Project File No. E5054
Location
Unincorporated El Granade Area
About the Project
The Pillar Point Harbor CCTV project includes inspection of approximately 27,000 feet of storm drain pipes ranging from 12 to 60 inches in diameter and associated manholes and other structures within the unincorporated El Granade Area.
In 2022, the County conducted inspections of approximately 5% of the areas system along Capistrano Rd (Area 1). The current project will include inspection of the remaining pipe and manholes in the unincorporated El Granade Area to determine if there are any defects or illicit connections to the existing system.
Public Works Contact
Carter Choi
Senior Engineer
cchoi@smcgov.org
650-363-4100
Contractor
Presidio Systems Inc.
Documents
CCTV Tentative Schedule
Schedule subject to change based on weather and other unforeseen conditions. The schedule will be updated, as needed.
UPDATES
-
February 2023 – Develop Scope of Work.
-
April 2023 – Kickoff Meeting held with Presidio Systems Inc.,
-
May 2023 – Presidio Systems. Inc schedule to start Closed-circuit Television (CCTV) of Storm Sewer Facilitates on May 22, 2023.
-
July 2023 – CCTV of Storm Sewer Facilities completed
-
September 2023 – Draft report reviewed.
-
October 2023 – Condition Assessment report finalized.