Project No. RW936; Project File No. E5047
Location
Bayside
About the Project
The work to be done consists of placing emulsion oil for the chip sealing of Tunitas Creek Road, Higgins Canyon Road, Purisima Creek Road, Verde Road, Lobitos Creek Road, Bear Gulch Road, Native Sons of Golden West Road, Stage Road, Swett Road, Star Hill Road, Old La Honda Road, Page Mill Road, Sunshine Valley Road, and Miramontes Road prior to the placement of chips by the County of San Mateo Road Division. In addition, Sunshine Valley Road will receive a full length and full width fog seal treatment after the installation of the chip-seal application.
Public Works Contact
Zack Azzari
Senior Engineer
zazzari@smcgov.org
650-363-4100
Contractor
VSS International, Inc. dba VSS Emultech
UPDATES
- June 21, 2022 - Bid Proposals were received
- September 30, 2022 – Construction completed
Schedule
Schedule subject to change based on weather and other unforeseen conditions. The schedule will be updated, as needed.
- Week 1
August 29 – Sunshine Valley Road / Miramontes Point Road
August 30 – Higgins Canyon Road
August 31 – Purisima Creek Road
September 1 – Verde Road
September 2 – Lobitos Creek Road - Week 2
September 5 – Labor Day – No Work
September 6 – Tunitas Creek Road
September 7 – Tunitas Creek Road
September 8 –Tunitas Creek RoadStage Road (N) of S/R 84 & Stage Road (S) of S/R 84
September 9 –Stage Road N of S/R 84Bear Gulch Road (D10) - Week 3
September 12 –Stage Road South of S/R 84Page Mill Road/Alpine Road (D9)
September 13 –Stage Road South of S/R 84Alpine Road (D9)
September 14 –Bear Gulch Road (D10)Old La Honda Road
September 15 –Bear Gulch Road (D10)/Page Mill, Old La HondaRoadRoadBear Gulch Road (D9)
September 16 –Alpine Road (D9), Bear Gulch Road (D9)Swett Road/Star Hill Road Segment Swett Road-Tunitas Creek Road - Week 4
September 19 –Alpine Road (D9) Swett Road & Star Hill RoadWeather delay
September 20 –Old La Honda RoadStar Hill Road &Native Sons Road &Bear Gulch Road (D10)-(pipe project segment)
September 21 –Bear Gulch Road (D9)Bear Gulch Road (D10)-(pipe project segment)
September 22 –Swett Road, Star Hill Road, and Native Sons of Golden WestSweeping/Off Haul
September 23 –Swett Road, Star Hill Road, and Native Sons of Golden WestSweeping/Off Haul