Project No. RW304; Project File No. S5100
Location
Street Name |
Length |
Average Width |
Approximate |
Meyn Road |
920 |
23 |
2,351 |
|
|
|
|
|
|
|
|
Seaside School Road |
1,300 |
16 |
2,311 |
Bear Gulch Road |
1,161 |
28 |
3,612 |
Jones Gulch Road |
2,800 |
28 |
8,711 |
Pomponio Creek Road |
14,200 |
21 |
33,133 |
Stage Road |
43,052 |
23 |
110,022 |
Eden West Road |
1,050 |
21 |
2,450 |
Canyon Road |
9,750 |
22 |
23,833 |
Portola State Park Road |
11,620 |
20 |
25,822 |
Goulson Street |
600 |
16 |
1,067 |
Water Lane |
2,150 |
19 |
4,539 |
Approx. Total |
88,603 |
|
217,851 |
About the Project
The work to be done consists of placing emulsion oil for the chip sealing of Meyn Road, Stage Road, Seaside School Road, Pomponio Creek Road, Goulson Street, Water Lane, Canyon Road, Eden West Road, Jones Gulch Road, Portola Sate Park and Bear Gulch Road prior to the placement of chips by the County of San Mateo Road Division.
Public Works Contact
Leo Chow
Senior Civil Engineer
lchow@smcgov.org
650-363-4100
Contractor
VSS International, Inc. dba VSS Emultech
UPDATES
- June 18, 2024 - Bid Proposals were received.
- October 2024 - Project is completed, roadway is opened to all traffic.
Schedule
-
Construction: September 16, 2024 to September 24, 2024
-
NTP was issued on September 9, 2024
Schedule subject to change based on weather and other unforeseen conditions. The schedule will be updated, as needed.
TBD