Project No. P29Y1, Project File No. E5065
Location
Sawyer Camp Trail, San Mateo County, CA
About the Project
The Sawyer Camp Trail Paving and Culvert Improvement Project aims to improve approximately 3.00 miles of pavement at Sawyer Camp Trail. This project also includes the improvement of culverts within the project limits to enhance storm drainage and flood protection in the trail.
Public Works Contact
Anthony Lum
Senior Engineer
alum@smcgov.org
650-363-4100
Contractor
TBD
UPDATES
-
March 2022 - 60% Design
-
April 2022 - 90% Design in development
-
May 2022 - 90% Design completed, 100% Design in development
-
June 2022 - 100% Design to be completed, JOC Contract in process
-
July 2022 - Tentative Construction Start Date: July 18, 2022
-
August 2022 - Construction Start Date: August 3, 2022
-
September 2022 - Construction Status: 60% Complete
-
October 2022 - Tentative Construction Completion Date: October 28, 2022
-
November 2022 - Sawyer Camp Trail Re-Opened to the public on October 29, 2022
Existing Culvert
Existing Pavement Condition
September 2022 - New HDPE Culvert with Headwall
September 2022 - New HDPE Culvert with Rock Dissipation
September 2022 - Pavement Repairs